My Council

Works and Services

Terrys Hill Road – Remediation and Bridge Replacment

UPDATE: 2 July

Terrys Hill Road – Road Remediation and replacement of Ransom River Bridge.

Parks and Wildlife have contracted Break O’Day Council to undertake these works which  will include:

  • 12 July – Remediation work of north of the bridge on Terrys Hill Road to ensure residents have an adequate detour while the bridge is replaced. This will have minimal traffic impact.
  • 19 July – Removal and Replacement of the Ransom River Bridge. These works will mean closure of the road and users will have to detour via Counsles Road. These works are anticipated to take 10 days.
  • Following the replacement of the bridge, Council will undertake road remediation works on Terrys Hill Road. This will have minimal disruption and is expected to take two weeks.

 

 

_____________________________________________________

The Gardens Road – Lyall Road and Jeanneret Crescent intersections

UPDATED 7 JULY

The guardrail will be installed by the end of July. This will complete the project.

UPDATED 8 June

Temporary signs will be replaced by permanent signs this week. Guardrails will be installed in July.

UPDATED 3 May

Council has been advised that the contractor will begin sealing of Gardens Road on 10 May, not May 7 as previously reported.

UPDATED 23 April

Bitumen Sealing for this project is scheduled for May 7.

Below update from the Break O’Day Council March Newsletter

These works, which aim to improve sight distances and construct a designated bus stops and footpath are progressing well. A new intersection on the corner of Lyall Road and the bus stop area have been completed, kerb and channel as well as designated footpath areas have been established. Much of the footpath and kerb and channel will be completed in time for Easter with some footpath the road sealing works held off until after Easter to minimise any traffic impacts over the holiday period. After Easter, the old bitumen surface will be torn up at both Southern and Northern ends of the work site so the Jeanneret Crescent intersection can be reconstructed and there will be smooth transitions between new and existing sections of Gardens Road. Bitumen sealing and installation of guardrails will then complete the project.

 

Work Type: Road reconstruction to improve sight distances. Construction of designated school bus stopping bays & footpaths.
Traffic Impacts:
  • Reduced speed limit for duration of work.
  • Single lane traffic movements with traffic lights and/or other controls operating.
  • Long delays will be rare but short delays should be expected.
Duration: It is expected that the work will be completed in late March however this is dependent on favourable weather conditions.

The sealing of the road surface will be completed when the surface has settled and is deemed suitable.

_____________________________________________________

Intake Bridge – Forest Lodge Road, Pyengana

UPDATED 8 June

The bridge has been replaced with a new structure with a 27 tonne gross load limit applied.

The reopening of Forest Lodge Road has however been delayed due to a landslip which we understand has occurred over the weekend. The new landslip is located on the western side of the South George River, which prevents public access until further notice. This is not related to the works already undertaken – this area is subject to landslips.

We will be reviewing engineering options to stabilise the land slip and arrange remediation works as soon as practicable.

UPDATED 26 April

Landslip remediation works will be completed by the end of April. These works had to be completed before our contractor is able to take a safe  possession of the site for installation of the new bridge.

The new bridge will be installed by the end of May.

_________________________________________________________________________________

Updated 31 March

Due to a landslip, these works have taken longer than planned. We are currently undertaking landslip remediation works with the project, including the installation of the bridge scheduled for completion by the end of April, 2021.

Intake Bridge on Forest Lodge Road has been closed due to its age and rate of deterioration making it unsafe for vehicle use. The bridge will be replaced by the end of May and the road re-opened to the public. It will however be load limited to 27 tonne gross. We will also be addressing some minor landslip in the area during this period. The bridge closure does prevents vehicles from having a direct route between St Columba Falls Road and Ralph Falls.

Vehicles under 8 tonne gross can still traverse the section of Forest Lodge Road from the Tasman Hwy north of Pyengana linking to the intersection with Mount Victoria Road.

The map below highlights the section of closed road.

Skyline Drive/Tasman Hwy Intersection

UPDATED 29 June

Major works are now completed.

Council crews will be back in Spring to plant some trees in the area.

UPDATED 8 June

Minor items are being cleaned up now. Temporary signs will remain in place while motorists and pedestrians become familiar with the new intersection.

UPDATED 24 March

Council will be undertaking works on behalf of Road Managers, State Growth at the Intersection of Skyline Drive, Beaumaris and the Tasman Hwy between April 12-30.

These works will include:

  • Designating a permanent bus stop
  • Shoulder widening
  • Some kerb and channel work
  • Footpath
  • Traffic island installation

There should be minimal traffic disruption while these works are undertaken but we ask that all vehicles obey signage in the area.

If you would like to see the technical drawings of the works they can be viewed here:

SKYLINE DRIVE DRAWINGS FOR RFT 

_____________________________________________________

St Helens Point Road – Between Aerodrome Road and the eastern end of Treloggens Track

UPDATED 8 June

Minor items are being cleaned up now. Temporary signs have been removed.

UPDATED 26 April

Road sealing for this project is scheduled for May 14 which will be followed by line marking – this will complete the project.

UPDATED 12 March

Civilscape Contracting are advising that they would like to undertake works at St Helens Point Road this coming weekend 13/3/21 – 14/3/21

Work hours for the weekend are outlined below and are compliant with EPA requirements and where possible will avoid undue disruption or inconvenience to road users and property owners.

  • Saturday 13/3/21 – no earlier than 8am and no later than 6pm
  • Sunday 14/3/21 – no earlier than 10am and no later than 6pm

They anticipate working within their current traffic management plan and do not envisage any further road closures/detours.

Work Type:  

SouthernTraffic Lane

  • Construction of parking bay between Egret Street and Osprey Drive.
  • Installation of kerb between Egret Street and Aerodrome Road.
  • Continuation of kerb east of Egret St to join existing kerb at the eastern end of Treloggens Track.

 

Northern Traffic Lane

  • Partial road reconstruction between Osprey Drive and Egret Street including installation of a small section of kerb.
Traffic Impacts:
  •  Reduced speed limit for duration of work.
  • Single lane traffic movements with traffic lights and/or other controls operating.
  • Long delays will be rare but short delays should be expected.
  • The contractor will liaise with property owners to ensure access to properties is maintained
Duration: It is expected that the work will be completed by early March however this is dependent on favourable weather conditions.

Below is a list of handy links for other service providers in our area:

Property Services:

TasWater:  13 6992

Aurora: 13 2004

SES: 132 500 (for damage to property during an emergency event like flood or fire)

Community Groups and Support organisations

St Helens Neighbourhood House:  6376 1134

Fingal Valley Neighbourhood House: 6374 2344

Medical Service Providers

Ochre Medical, St Helens: 6376 1777

St Marys Community Health Centre: 6387 555

St Helens District Hospital: 6387 5570

Education and Employment Service Providers

St Helens District High School: 6376 7177

St Marys District School: 6372 3900

Break O’Day Trade Training Centre: 1300 655 307

You can find more information on the Great Eastern Drive Upgrades on the Department of Transport website here:

 

 

For information on Waste and Recycling Collection click here.

Road Works – State Government

You can find a full list of State Growth works here.